city of grand junction public works projects 4

City of Grand Junction Projects with Travel Restrictions

Chip Seal Program

This week’s chip sealing will take place on streets located in the northwest part of the City.

Monday:

  • F 3/8 Road west of 24 ½ Road
  • F ¾ Road from 24 ¾ Road to 24 ½ Road
  • Brookwillow Loop east of 24 ½ Road
  • Fountainhead Blvd. between 24 ¾ Road and G Road
  • E.  Harbor Cir. East of Fountainhead Blvd.

Tuesday:

  • 24 ¾ Road north of Hwy 6&50
  • Interlochen Court east of Fountainhead Blvd.
  • Lake Park Drive/Court east of Lochwood Way
  • Eider Court south of lake Park Drive
  • Lochwood Way/Court south of Merganser Drive
  • Merganser Drive between Wigeon Drive and Lochwood Drive
  • Wigeon Drive between Fountainhead Blvd. and Merganser Drive
  • Jakarlin Court east of 24 ¾ Road
  • 24 ¾ Road north of G Road
  • Payton Court west of 24 ¾ Road
  • G ¼ Road between 24 ½ Road and Monument View Drive

Wednesday:

  • Roaring Fork Drive between 24 ¾ Road and Monument View Drive
  • Monument View Drive north of Cimarron Drive
  • Cimarron Drive west of 24 ¾ Road
  • N.Valley Drive between Cimarron Drive and Roaring Fork Drive
  • Tall Grass Drive west of 23 Road
  • Long Acre Drive between Tall Grass Drive and G Road
  • 23 ½ Road north of I-70 Frontage Road
  • Expect possible short term street closures resulting in moderate traffic delays
  • Alternate route advised

    Fiber Optic installation for new Fire Station #6

  • Shoulder work along west side of 27 Road between Horizon Drive and 729 27 Road
  • Please slow down through construction zone
  • Delays will be minimal

2020 Asphalt Overlay Program 

This week’s activities will include the following (weather dependent):

  • Traffic delays can be expected
  • Rolling lane closures will be utilized

Concrete Removal and Replacement / Manhole Adjustments:

  • Colex Dr. area

Asphalt Milling (Night Work)

  • Horizon Ave. – 26 ½ Rd. to 12th St
  • G Rd. – HWY 6&50 to 23 Rd.
  • 23 Rd. – G Rd. to Bridge over I-70
  • Market St. – Patterson Rd. to F ½ Rd.
  • Foresight Circle

Asphalt Paving

  • Summer Hill Way – 26 ½ Rd to Spring Crossing
  • Galaxy Ct/Galaxy Dr. – G Rd. to N. End of Pavement
  • Centauri Ct/Centauri Dr. – G Rd. to N. End of Pavement
  • Beta Pl. – Galaxy Dr. to Centauri Dr.
  • Alpha Pl. – Galaxy Dr. to Centauri Dr.
  • G 3/8 Rd. – 26 ½ Rd. to Flower St.
  • Flower St. – G 3/8 Rd. to N. End of Pavement
  • G ½ Rd. – 26 ½ Rd. to Flower St.
  • Tulip Dr. – G ½ Rd. to Flower St.
  • Chestnut Ct. – 26 ½ Rd. to E. End of Pavement

Alley Improvement Project from 10th Street to 11th Street between Ute Avenue and Pitken Avenue

  • 11th Street will be closed to thru traffic
  • No alley access
  • Anticipated completion – Late July

Contact: Greg LeBlanc, Sr. Assistant to the City Manager 970-244-1557 or gregoryl@gjcity.org

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s