City of Grand Junction Projects with Travel Restrictions
Raw Water Line Construction – 5th Street Bridge
- North Bound 5th Street traffic will be reduced to one lane
- Expect delays
- 35 mph speed limit will be enforced
- Anticipated completion – April
31 Road between D ½ Road and E Road, Utility Construction
- 31 Road closed to thru traffic
- Access for residents will be provided
- Detour route is in place
- Anticipated completion – April
Court Road between Orchard Avenue and Bookcliff Avenue, Utility Construction
- Court Road between Orchard Avenue and Bookcliff Avenue will be closed to thru traffic
- Access for local residents will be provided
- Detour route will be in place
- Anticipated completion – April
Riverside Trail Repairs/Replacement west of 5th Street Bridge
- Approximately 2,000 of trail along various locations will be under construction
- Please follow well-marked detour
- Anticipated completion – April
Non-City of Grand Junction Projects with Travel Restrictions
22 Road between J Road and K Road, Bridge Replacement Project – Mesa County Project
- 22 Road is closed to through traffic
- Work hours will be 8:00 a.m. – 4:00 p.m., Mon. – Fri.
- Access will be provided for local residents at all times
- A well-marked detour will be in place
- Anticipated completion – April.
Orchard Avenue Reconstruction, Normandy Drive to 29 Road – Mesa County
- Work will resume Monday, March 2nd
- Minimal traffic impacts are anticipated with exception of paving days
- Orchard Avenue will be closed to thru traffic during the week of March 30th for paving
- Anticipated final completion – April
Contact: Greg LeBlanc, Sr. Assistant to the City Manager 970-244-1557 or gregoryl@gjcity.org