City of Grand Junction Projects with Travel Restrictions
F ½ Road Closure West of 31 Road – Lewis Wash Bridge Replacement Project
- F ½ Road will be closed to through traffic between 30 Road and 31 Road, 24/7
- Detour route will be in place
- Residents living west of Lewis Wash and Thunder Mountain Elementary School traffic use 30 Road
- Residents living east of Lewis Wash including Allegheny Drive use 31 Road
- Anticipated completion – mid April.
Reeder Mesa Road – Water Line Replacement
- Watch for truck and heavy equipment traffic along both Reeder Mesa Road and Lands’ End Road
- Expect occasional daytime closures
- Message boards at each end of Reeder Mesa Road will give specific closure dates
- Detour route will be in place on days of closure
- Anticipated completion – May.
Two Rivers Convention Center – Remodel Project
- Main Street will be closed to both pedestrian and vehicle traffic between 1st Street and 2ndStreet, Monday only, 6am to 6pm
- Detour route will be in place
- Anticipated completion – Monday, April 8.
City of Grand Junction Annual Spring Clean-Up Program
- Spring clean-up starts this week north of North Avenue
- Motorists can expect delays and short-term street closures
- Completion Friday, April 19.
Non-City of Grand Junction Projects with Travel Restrictions
32 Road Sewer Line Replacement Project – Clifton Sanitation District Project
- Watch for utility construction (various locations) along 32 Road between I-70B and D Road
- Please slow down through the work zones and obey traffic control signs and personnel
- Motorists may experience intermittent lane closures and detours
- Anticipated completion – September.
22 Road and H Road Utility Construction – Private Development
- H Road is closed to through traffic between 22 Road and 23 Road
- Access for local residents will be provided
- Detour route is in place
- Anticipated completion – May.
Contact: Sam Rainguet, Communications Manager 970-244-1507 or samr@gjcity.org